SR 24 FROM N OF SR 12/MORGAN TO N OF APALACHEE RIVER/OCONEE
Project ID: 0013617 Notice to Proceed Date:
Project Manager: Ashley M. Willoughby Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: Morgan, Oconee Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 017, 046 Construction Contractor:
State House District: 114, 121 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
Widening of SR 24/US 441 to four (4) 12-foot lanes from the Madison Bypass to just north of the Apalachee River. From the beginning terminus of the project, the concept would proceed north and would extend the existing 5 lane section north approximately 1100 feet. Just north of this section, the concept would transition to a four lane, 32-foot depressed grassed median with a rural shoulders (10¿ graded (6.5¿ paved) outside shoulders). The proposed alignment will follow the existing alignment along SR24/US 441 for the length of the project and end just north of Apalachee River in Oconee County. PI # 0013613 would begin at the ending terminus of 0013617. Existing right-of-way along US 441/SR 24 is 130 feet. The proposed right-of-way would vary from 130 feet to 250 feet for the length of the project. The speed design would be 55 mph. The project length would be approximately 8.46 miles.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2016$4,700,042.8510/19/2018
PE (Preliminary Engineering)2019$3,520,000.0010/19/2018
ROW (Right of Way)2022$6,380,000.002/11/2021
UTL (Utilities)2026$1,725,390.138/9/2024
CST (Construction)2026$83,657,637.719/6/2024