I-20 FRONTAGE ROAD FROM SR 12 TO CR 249/OLD MILL ROAD
Project ID: 0018363 Notice to Proceed Date:
Project Manager: Kathe Ahmed Construction Percent Complete: 99.72%
Office: Alternative Delivery Current Completion Date:
County: Morgan, Walton Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 017 Construction Contractor: C. W. MATTHEWS CONTRACTING CO., INC.
State House District: 112, 114 Preconstruction Status Report
Project Type: New Construction Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
¿ The frontage road will be constructed parallel to I-20 to the north and consisting of four travel lanes, a 20-foot raised median, rural shoulders, and a multi-use path.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2022$1,680,000.00 
PE (Preliminary Engineering)2023$2,833,153.43 
CST (Construction)2023$59,750,000.006/14/2022
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports