ROCK QUARRY ROAD FROM EAGLES LANDING PKWY TO SR 42/SR 138
Project ID: 0015090 Notice to Proceed Date:
Project Manager: Michael Vincent Hamilton Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: Henry Work Completion Date:
Congressional District: 013 Construction Contract Amount:
State Senate District.: 010 Construction Contractor:
State House District: 091, 116 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
Rock Quarry Road project is a widening project beginning at Eagles Landing Parkway north and ending at SR 42/138. The proposed project will consist of two-11 foot inside lanes, two-12 foot outside lanes, a 20 foot raised median, and a multi-use trail for pedestrians. The total miles for the widening project is 2.60 in length. This project is located in the 13th Congressional district. Rock Quarry Road in Henry County is classified as an urban minor arterial. This project is currently identified in the Atlanta Regional Commission's (ARC) Regional Transportation Plan (RTP), Plan 2040, and is included in the Transportation Improvement Program (TIP). This project is located within the Atlanta MPO boundary and is listed in the TIP as HE-161A.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2017$1,500,000.00 
ROW (Right of Way)2020$7,171,200.00 
UTL (Utilities)2025$9,402,218.794/8/2024
CST (Construction)2025$39,396,701.271/31/2024