project_id
M006333
SR 6 FROM SR 5 TO FULTON COUNTY LINE
Project ID:
M006333
Notice to Proceed Date:
Project Manager:
Kevin Matthew Bailey
Construction Percent Complete:
84.73%
Office:
Maintenance
Current Completion Date:
County:
Douglas
Work Completion Date:
Congressional District:
013
Construction Contract Amount:
State Senate District.:
035
Construction Contractor:
E. R. SNELL CONTRACTOR, INC.
State House District:
061
Preconstruction Status Report
Project Type:
Maintenance
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
project_id
M006333
Project Description:
This project, selected by the District Maintenance Office, is the resurfacing of SR 6 to improve the roadways current OCI Score.
Activity
Program Year
Cost Estimate
Date of Last Estimate
MCST (Maintenance Construction)
2023
$6,895,484.63