SR 10LP @ SR 10 IN ATHENS
Project ID: 122890- Notice to Proceed Date:
Project Manager: Oluchukwu Eziogonnaya Anyaebosi Construction Percent Complete: 19.62%
Office: Program Delivery Current Completion Date:
County: Clarke Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 046 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 120 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
This project is to construction a new loop ramp from Atlanta Highway westbound to SR 10 Loop southbound, realigning the existing loop ramp from Atlanta Highway eastbound to SR 10 Loop northbound, and widening Atlanta Highway by adding four lanes and lengthening several turn lanes. The project also includes improvements to the Huntington Road and Atlanta Highway intersection.
ActivityProgram YearCost EstimateDate of Last Estimate
ROW (Right of Way)1998$425,000.001/31/2011
PE (Preliminary Engineering)1999$5,019,763.35 
ROW (Right of Way)2004$869,224.001/31/2011
ROW (Right of Way)2011$11,770,000.001/31/2011
CST (Construction)2023$61,646,096.8610/14/2022