I-75 FROM I-675 TO S OF SR 155 - EXPRESS LANES
Project ID:
0020636
Notice to Proceed Date:
Project Manager:
Marlo Letrice Clowers
Construction Percent Complete:
%
Office:
P3
Current Completion Date:
County:
Henry
Work Completion Date:
Congressional District:
003, 010, 013
Construction Contract Amount:
State Senate District.:
010, 017, 025
Construction Contractor:
State House District:
078, 091, 115, 116
Preconstruction Status Report
Project Type:
Other
Construction Status Report
Project Status:
Construction Work Program
More Information...
Right of Way Authorization:
Contact Us
project_id
0020636
Project Description:
Activity
Program Year
Cost Estimate
Date of Last Estimate
PE (Preliminary Engineering)
2024
$10,000,000.00
8/9/2024
PE (Preliminary Engineering)
2025
$13,000,000.00
8/9/2024
PE (Preliminary Engineering)
2026
$25,000,000.00
8/9/2024
ROW (Right of Way)
2028
$70,013,411.00
CST (Construction)
2029
$430,000,000.00
Project Search (TransPI) Map