SR 212 @ LAKE JACKSON 13.9 MI S OF COVINGTON
Project ID: 0013603 Notice to Proceed Date:
Project Manager: Recheal Mcmullin Construction Percent Complete: 56.92%
Office: Program Delivery Current Completion Date:
County: Jasper, Newton Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 017, 025 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 114, 118 Preconstruction Status Report
Project Type: Replacement Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The project proposes to replace the existing bridge on SR 212 at Lake Jackson in Newton/Jasper Counties, located 13.9 miles south of Covington, GA. The proposed project begins approximately 575 feet northwest of the existing bridge and extends southeast 917 feet, for an approximate length of 2,196 feet (0.42 miles). Proposed is a new 740-foot long by 43.25-foot wide bridge over Lake Jackson that will be constructed parallel to the existing bridge on the east side. Traffic will be maintained on the existing bridge during construction.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2016$1,960,268.83 
ROW (Right of Way)2020$3,140,000.002/20/2020
CST (Construction)2023$16,171,169.9010/8/2020