SR 22 @ CR 715/KNOXVILLE ROAD
Project ID: 0009960 Notice to Proceed Date:
Project Manager: Leo Perez Construction Percent Complete: 94.08%
Office: Program Delivery Current Completion Date:
County: Bibb Work Completion Date:
Congressional District: 002 Construction Contract Amount:
State Senate District.: 018, 026 Construction Contractor: C. W. MATTHEWS CONTRACTING CO., INC.
State House District: 142, 145 Preconstruction Status Report
Project Type: Safety Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
This project proposes to install a roundabout at the intersection of US 80/SR 22/Eisenhower Parkway and CR 715/Knoxville Road. Once complete, the project will improve the level of services and anticipated to reduce crash frequency and severity.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2016$969,717.603/10/2010
ROW (Right of Way)2021$270,000.0010/8/2020
CST (Construction)2022$2,334,962.557/15/2020
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports