PANOLA RD @ I-20 FM FAIRINGTON RD TO SNAPFINGER WOODS DR
Project ID: 0002868 Notice to Proceed Date:
Project Manager: Gretel Sims Construction Percent Complete: %
Office: Program Delivery Current Completion Date:
County: DeKalb Work Completion Date:
Congressional District: 004 Construction Contract Amount:
State Senate District.: 041, 055 Construction Contractor:
State House District: 084, 091, 093 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Construction Work Program More Information...
Right of Way Authorization: Contact Us
Project Description:
This project proposes reconstruction of the Panola Road at I-20 Interchange as a Diverging Diamond Interchange (DDI) in order to improve traffic, multi-modal transportation and safety. The project will also provide a new bridge capable of providing adequate clearance for future widening along I-20.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2011$5,980,176.005/5/2011
ROW (Right of Way)2022$39,940,000.003/23/2022
UTL (Utilities)2025$1,795,800.0010/30/2024
CST (Construction)2025$53,926,706.7110/25/2024
Project Search (TransPI) Map
 Project Documents

Approved Concept Reports

 
 
 

Project Outreach Archive