Project Milestones
Project milestones for the Johnson Ferry/Abernathy Road Widening Projects include the following:
Phase I : Public Involvement
- March – April 2002: Develop Public Involvement Plan
- May 2002: CAC Meetings
- December 2002: Public Information Meeting
- February and March 2003: CAC Meetings
- March 2003: Public Information Meeting
- June 2003: CAC Meeting
Phase II: Concept Development
- April – November 2002: Prepare Conceptual Plans with Alternative Designs
- July 2003: Prepare Concept Report
Phase III: Traffic Studies
- April 2002: Travel Demand Modeling and Projections
- April – October 2002: Traffic Model Analysis
- March – April 2003: Prepare Traffic Studies Report
Phase IV: Environmental Studies and Analyses
- April 2002 – March 2003: Preliminary Studies and Analyses; Coordination with Resource Agencies
- July 2003 – December 2004: Complete Environmental Studies and Prepare Draft Environmental Assessment
- March 2005: Draft Environmental Document Public Hearing
Phase V: Preliminary Plans
- April 2005: Preliminary Field Plan Review
Phase VI: Right of Way Approval and Acquisition
- May 2005 – July 2005: Completion of right-of-way plans
- July 2005: Approval of the right-of-way plans
- August 2005: Begin the acquisition of right-of-way
Phase VII: Final Plans
- Letting: January 2009 (Expect 29 months of construction)