I-285 FROM SR 14/FULTON TO CR 2838/PACES FERRY ROAD/COBB
Project ID: M005889 Notice to Proceed Date:
Project Manager: Arthur Mckinley Wilson II Construction Percent Complete: 99.29%
Office: Maintenance Current Completion Date:
County: Cobb, Fulton Work Completion Date:
Congressional District: 005, 011, 013 Construction Contract Amount:
State Senate District.: 006, 038, 039 Construction Contractor: GOSALIA CONCRETE CONSTRUCTORS, INC.
State House District: 039, 040, 053, 055, 061, 062, 064 Preconstruction Status Report
Project Type: Maintenance Construction Status Report
Project Status: Complete More Information...
Right of Way Authorization: Contact Us
Project Description:
This project, selected by the District Maintenance Office, is the concrete rehabilitation of SR 407 (I-285)to improve the roadway's current condition.
ActivityProgram YearCost EstimateDate of Last Estimate
MCST (Maintenance Construction)2019$23,634,994.89 
Project Search (TransPI) Map