project_id
0009011
SR 53 FROM SR 24/US 441 TO CR 274/HOG MTN - PHASE II
Project ID:
0009011
Notice to Proceed Date:
Project Manager:
Kesha Wynn
Construction Percent Complete:
66.88%
Office:
Program Delivery
Current Completion Date:
County:
Oconee
Work Completion Date:
Congressional District:
010
Construction Contract Amount:
State Senate District.:
046
Construction Contractor:
E. R. SNELL CONTRACTOR, INC.
State House District:
121
Preconstruction Status Report
Project Type:
Reconstruction/Rehabilitation
Construction Status Report
Project Status:
Under Construction
More Information...
Right of Way Authorization:
Contact Us
project_id
0009011
Project Description:
The project consists of widening and reconstruction of SR 53/Mars Hill Road from SR 24/US 441 to CR 274/Hog Mountain Road and will be approximately 1.14 miles in length. This project is located approx. 1 mile south of the Oconee County Line and northwest of Watkinsville, GA.
Activity
Program Year
Cost Estimate
Date of Last Estimate
PE (Preliminary Engineering)
2012
$104,999.98
2/4/2011
ROW (Right of Way)
2014
$3,870,000.00
2/14/2014
CST (Construction)
2021
$13,297,271.14
7/1/2020