SR 53 FROM SR 24/US 441 TO CR 274/HOG MTN - PHASE II
Project ID: 0009011 Notice to Proceed Date:
Project Manager: Kesha Wynn Construction Percent Complete: 66.88%
Office: Program Delivery Current Completion Date:
County: Oconee Work Completion Date:
Congressional District: 010 Construction Contract Amount:
State Senate District.: 046 Construction Contractor: E. R. SNELL CONTRACTOR, INC.
State House District: 121 Preconstruction Status Report
Project Type: Reconstruction/Rehabilitation Construction Status Report
Project Status: Under Construction More Information...
Right of Way Authorization: Contact Us
Project Description:
The project consists of widening and reconstruction of SR 53/Mars Hill Road from SR 24/US 441 to CR 274/Hog Mountain Road and will be approximately 1.14 miles in length. This project is located approx. 1 mile south of the Oconee County Line and northwest of Watkinsville, GA.
ActivityProgram YearCost EstimateDate of Last Estimate
PE (Preliminary Engineering)2012$104,999.982/4/2011
ROW (Right of Way)2014$3,870,000.002/14/2014
CST (Construction)2021$13,297,271.147/1/2020